Forensic / Delay Schedule Analysis – Summary Graphic Report in 1 Page

After performing delay analysis work in Primavera P6 or MS Project, we should make a summary graphic report for high-level manager. It would be difficult to get the overview of the analysis with a detail report like the following picture:

A simple bar chart or timeline would be more effective and I would like to show a few samples as follows.
Summary

Time Impacted Analysis (in Multi Base /Window)

As-Built But-For / Collapsed As-Built


Leave a comment